Extension Update #12

Extension Update #12

What has happened? Phases 1 and 2 (groundworks, foundations and first floor concrete floor) have now been completed, Alhamdulillah. What will the impact be to you? For now, entrance arrangements remain unchanged for brothers and sisters. However please look out for...
IANL Extension Update #11

IANL Extension Update #11

What has happened? Completion of reinforced floor and walls for the new front entrance Manufacturer sign-off of waterproofing (tanking) between the masjid and the neighbouring property Taylor Wimpey have taken back their site for demolition There is a delay to...
IANL Extension Update #10

IANL Extension Update #10

What has happened? Underpinning of the neighbouring property has been completed Waterproofing (tanking) between the masjid and the underpinned property has been designed and applied. This has caused the plan to slip by approximately 2 weeks Foundations for the new...
IANL Extension Update #9 – 6 May

IANL Extension Update #9 – 6 May

What has happened? Underpinning of the neighbouring property is close to completion Pre-ramadan access arrangements have been restored Building works have restarted and are back in full swing Taylor Wimpey have served notice to take back their site in order to...
IANL Extension Update #7 – 1 Feb

IANL Extension Update #7 – 1 Feb

hat is happening? Underground works such as drainage, foundations, utilities etc. beneath the car park are complete. All but one of the concrete columns in the car park area are ready to be poured. The car park area has been flattened. New walkway has been prepared as...