Phase 3 – Stage 1
- The next main stage of works is due to commence shortly
- There will be part road closure outside the masjid to enable this
- At some point in the near future the front entrance will be closed for approximately one week
- During this period brothers and sisters will only be able to use the Rosemont entrance to enter the masjid
- This will allow the steel for the front extension to be erected and concrete floors to be put down
- We hope to have this work done within four days of the commencement of works
- The start days of the works is dependent on the Council giving permission for this
What will the impact be to you?
- When the work commences brothers and sisters will all enter the masjid from the sisters entrance at Rosemount Avenue for approximately one week
- The front entrance and road will be closed during this time please check your route to the masjid if you are driving and expect more traffic
- We will endeavour to have this disruption completed before applicable jummah
What’s happening next
- Wooden floors and the wooden roof structure will built next
- Fundraising for the completion of Phase 3 is ongoing
Please support the Extension Project
Please continue to say dua for the success of the extension project.
Donations towards the extension project can be made directly through the IANL website and in the masjid.