Front Extension Update

Checkout the latest news on the Front Extension Redevelopment project and also see a 3D flythough of the plans.

Latest News

IANL Extension Update #11

IANL Extension Update #11

What has happened? Completion of reinforced floor and walls for the new front entrance Manufacturer sign-off of waterproofing (tanking) between the masjid and the neighbouring property Taylor Wimpey have taken back their site for demolition There is a delay to...

read more
IANL Extension Update #10

IANL Extension Update #10

What has happened? Underpinning of the neighbouring property has been completed Waterproofing (tanking) between the masjid and the underpinned property has been designed and applied. This has caused the plan to slip by approximately 2 weeks Foundations for the new...

read more
IANL Extension Update #9 – 6 May

IANL Extension Update #9 – 6 May

What has happened? Underpinning of the neighbouring property is close to completion Pre-ramadan access arrangements have been restored Building works have restarted and are back in full swing Taylor Wimpey have served notice to take back their site in order to...

read more
IANL Extension Update #7 – 1 Feb

IANL Extension Update #7 – 1 Feb

hat is happening? Underground works such as drainage, foundations, utilities etc. beneath the car park are complete. All but one of the concrete columns in the car park area are ready to be poured. The car park area has been flattened. New walkway has been prepared as...

read more

Donate Online

Please help support this project. You can make donations either as a single payment or monthly.

3D Fly-through of Plans

Here are the latest plans for the Front Extension

Donate Online

Please help support this project. You can make donations either as a single payment or monthly.