What is happening?

  • The electricity consumer unit has now been moved and we are awaiting a certificate to be provided
  • Foundation work next to main entrance has begun
  • Steels have been received for the columns and are being prepared
  • Thames Water have approved works on the main road. We await dates
  • Foundation works in the car park have been completed

What will the impact be?

  • The Taylor Wimpey (Homebase) entrance will be in constant use
  • Shoe rack spaces are reduced in the basement
  • Some of the basement continues to be boarded off, thereby reducing capacity

Instructions for IANL users

  • Please do not block the entrance to the Taylor Wimpey (Homebase) site by parking there, as the workers will be using this frequently
  • Please keep out of the hoarded areas and supervise children at all times

What’s happening in the next fortnight or so

  • The manholes are set to be finished
  • The underground attenuation tanks will be installed and covered
  • Options for a temporary entrance while the main entrance is demolished will be presented by the contractor

Ramadan

  • We are planning to have use of the car park during Ramadan for additional (outside) prayer spaces

Help us get ready for Phase 3

We urgently need to raise funds so that we can start Phase 3 without delay. This phase will involve building the structure to Roof Level and is aimed to start after Ramadan.

The Prophet (ﷺ) said, “Whoever builds a mosque, desiring thereby Allah’s pleasure, Allah builds for him the like of it in paradise.” [Bukhari]

Your donation will help extend the Masjid and build the facilities we need for the next generation.