What has happened?
- Phases 1 and 2 (groundworks, foundations and first floor concrete floor) have now been completed, Alhamdulillah.
What will the impact be to you?
- For now, entrance arrangements remain unchanged for brothers and sisters. However please look out for signage in the coming weeks for any changes.
Instructions for IANL users
- Do not park in front of the Taylor Wimpey (Homebase) entrance. It is in constant use by heavy machinery
- Continue to use the new main temporary entrance to the masjid. Note that entrances may be opened and closed at short notice so please observe signage
- Please keep out of the hoarded areas and supervise children at all times
What’s happening next
- Widening of Rosemont entrance gates to comply with fire safety regulations
- Removal of scaffolding from the ground floor of the front extension
- Agree scope and budget of next contract to commence Phase 3 works imminently, based on currently available funds
- Fundraising to for complete of Phase 3 is ongoing
Please support the Extension Project
Please continue to say dua for the success of the extension project.
Donations towards the extension project can be made directly through the IANL website and in the masjid.