What has happened?
- Underpinning of the neighbouring property is close to completion
- Pre-ramadan access arrangements have been restored
- Building works have restarted and are back in full swing
- Taylor Wimpey have served notice to take back their site in order to commence their demolition works
- We have requested partial retention from Taylor Wimpey and are awaiting a decision
What will the impact be to you?
- Please continue to use the temporary front entrance
- Access to sisters areas remains unchanged
Instructions for IANL users
- Do not park in front of the Taylor Wimpey (Homebase) entrance
- Continue to use the new main temporary entrance to the masjid
- Please keep out of the hoarded areas and supervise children at all times
What’s happening in the next two weeks
- Work will begin on the foundations for the new front entrance
Please support the Extension Project
Please continue to say dua for the success of the extension project.
Donations towards the extension project can be made directly through the IANL website and in the masjid.