What has happened?

  • Completion of reinforced floor and walls for the new front entrance
  • Manufacturer sign-off of waterproofing (tanking) between the masjid and the neighbouring property
  • Taylor Wimpey have taken back their site for demolition
  • There is a delay to completion of Phase 2 currently stands at 3-4 weeks due to a combination of factors

What will the impact be to you?

  • An entrance will be available from the front of the building for the majority of the next 2 weeks. If this entrance has to be closed, signs will be put up conveying alternative access arrangements
  • Access to sisters areas via Rosemont Avenue may also be closed at short notice to facilitate works. Please follow signs if you encounter this

Instructions for IANL users

  • Do not park in front of the Taylor Wimpey (Homebase) entrance. It is in constant use by heavy machinery 
  • Continue to use the new main temporary entrance to the masjid. Note that entrances may be opened and closed at short notice so please observe signage 
  • Please keep out of the hoarded areas and supervise children at all times

What’s happening in the next two weeks

  • Commencement of scaffolding and propping for first floor ring beam
  • Widening of Rosemont entrance to comply with fire regulations